EV Charging Infrastructure
Planning · GTA Region
⚡
EV Charging Infrastructure
Module 7 — EV station planning at hotels, homestays, hospitals, roadside & commercial areas across GTA
⚡
Proposed Stations
84
Across GTA jurisdiction
✅
Sites Approved
23
Phase 1 locations
🔌
Charging Points
168
Total planned capacity
💰
Est. Annual Revenue
₹3.2Cr
Revenue share with GTA
EV Station Locations — Proposed & Approved
Proposed EV Station Sites
| Location | Site Type | Chargers | Phase | Status | GTA Revenue Share |
| Darjeeling Mall Road | Commercial Area | 4 | Phase 1 | Approved | 20% |
| Himalayan Nest Homestay | Homestay | 2 | Phase 1 | Approved | 15% |
| Kurseong District Hospital | Hospital | 2 | Phase 1 | Approved | 10% |
| Kalimpong Town Centre | Commercial | 4 | Phase 1 | Under Review | 20% |
| NH-10 Roadside (km 42) | Highway | 6 | Phase 2 | Proposed | 25% |
| Siliguri Gateway Hub | Multi-purpose | 10 | Phase 2 | Proposed | 20% |
Revenue Sharing Model
💡 GTA receives revenue share from each charging station operated by SAIARD
Commercial Areas (25% share)₹82L/yr
Highway Stations (20% share)₹1.1Cr/yr
Hotels & Homestays (15% share)₹38L/yr
Hospitals & Institutions (10%)₹18L/yr
Project Investment Overview
Phase 1 Investment
₹4.8 Cr
23 stations · 46 charging points
Phase 2 Investment
₹9.2 Cr
61 stations · 122 charging points
Implementation Phasing
| Phase | Timeline | Stations | Focus Areas | Status |
| Phase 1 | 2026 Q2–Q3 | 23 | Darjeeling, Kurseong, Kalimpong town centres | Approved |
| Phase 2 | 2026 Q4 – 2027 Q2 | 38 | Highway corridors, homestays, hospitals | Planning |
| Phase 3 | 2027 Q3+ | 23 | Remote areas, trekking routes, Sandakphu | Proposed |